Work Session and Regular Meeting
Meeting Date: 04/28/2020  
Department: Public Works  
Pillars: Excellence in Transportation Systems
Milestones: Establish an intentional culture throughout the organization that is based on continuous improvement, excellence, and adherence to our core values

AGENDA CAPTION:
Present and Discuss a Status Update on the Midway Road Reconstruction Project.
BACKGROUND:
In 2012, Addison voters approved $16 million in General Obligation bonds for the revitalization of Midway Road from Spring Valley Road to Keller Springs Road. In April 2018, Council authorized staff to proceed with including the newly adopted Master Transportation Plan that includes wider medians and an off-street trail.
 
On November 12, 2019 Staff presented an update on the Midway Road Reconstruction Project  This included investigating the possibility of using Archer Western Herzog (AWH), DART's contractor who is designing and building the Silver Line Rail Project, as the construction contractor for the reconstruction of Midway Road.
 
This presentation will update Council on the activities that have occurred since that time. This includes project design, property acquisition activities, the evaluation and selection of a general contractor for the project, and the updated project budget and timeline.
RECOMMENDATION:
Information only, no action required.
Attachments
Presentation - Midway Road Reconstruction Project Update