Present and Discuss an Update on the Design of the Midway Road Reconstruction Project.

 

BACKGROUND:
In 2012, Addison voters approved $16,000,000 in General Obligation bonds for the reconstruction of Midway Road. The design of the reconstruction is 60% complete and 90% design is expected in early April 2019. Staff will provide Council an update on the design that will include updated project scope and cost estimates, project schedule, communications plan, and anticipated land acquisition activities.

The presentation is attached.     
RECOMMENDATION:
Information only. No action required. 