AGENDA CAPTION:
Consider Action on a
Resolution Approving an Agreement Between the Town of Addison and Criado and Associates, Inc. for Professional Engineering Services Related to the Rawhide Creek Drainage Basin - Problem Area No. 7 Drainage Improvements Project and Authorizing the City Manager to Execute the Agreement
in an Amount Not to Exceed $343,591.
BACKGROUND:
The Storm Drainage System Assessment and Capital Improvement Program prepared for the Town of Addison by Halff Associates in August 2017 identified improvements that are needed in the Rawhide Creek Drainage Basin.
Criado and Associates, Inc. (Criado) was qualified through a Request for Qualifications process in 2017 to perform design, project management, and construction management related services for the Town. Criado was selected to perform the design work for the Rawhide Creek Drainage Basin Improvements due to their experience with previous drainage projects and familiarity with the Town’s standards and specifications.
This project includes the design of drainage improvements along the residential streets of Waterside Court, Waterford Drive, Les Lacs Avenue, Beau Park Lane, and Brookwood Lane. The drainage improvements will follow the trail south from Brookwood Lane and run west along the linear park connecting to the existing storm drain system at Marsh Lane (see recommended plan exhibit attached below).
Criado will provide the following services under this agreement:
Survey of the project area
Geotechnical investigation
Sub-surface utility location to determine the extent of existing utilities in the area
Design of the storm drain improvements
Bidding phase services
Design support during construction such as review of shop drawings and Requests for Information
Design for this project is anticipated to take 10 months to complete. Construction is anticipated to begin in early 2022. This project is budgeted in the Storm Water Capital Projects Fund.
RECOMMENDATION:
Administration recommends approval.
Attachments
Resolution - Agreement with Criado and Associates for Rawhide Creek Basin Area #7
Exhibit - Recommended Plan